The Nelson Mandela Bay municipality has launched an initiative to take over management of the critical Nooitgedacht water treatment plant expansion project which remains in limbo due to a dispute between the contractor and the implementing agent appointed by the national government.
Mayor Nqaba Bhanga said on Wednesday though the money owed to the contractor had since been paid over by the Amatola Water Board, there was no clarity as to when the delay would end, and this situation was unacceptable.
“This is a national department of water and sanitation project but the situation is exposing us to adverse risk.
“So we are now fighting to be delegated the responsibility to complete the project ourselves and we have made a proposal in terms of the standing legislation that will allow us to assume this role.
“In terms of section 41 of the Intergovernmental Relations Framework Act, we have formally declared a dispute with the department of water and sanitation.
“We have no option. This will provide us with the platform to resolve this situation.”
Bhanga said he was hoping the department would respond positively.
“We will not hesitate to take legal action if they do not.”
Water and sanitation department spokesperson Sputnik Ratau confirmed receipt of the dispute lodged by the metro.
“Correspondence is noted. Once the due processes have been followed and a determination is arrived at, the metro will be informed.”
The Nooitgedacht Water Treatment Works is situated in Sunland near Addo at the southern end of a 400km system of rivers, canals and pipes which transfers water from the Gariep Dam on the border of the Eastern Cape and the Free State.
The water is treated at the plant — and also at the temporary Grassridge treatment works — and then channelled into the metro.
Phase three of the project to expand the treatment plant was launched in 2017, with a budget of R318m from the department of water and sanitation.
It was initially due to be completed in March 2019, but has repeatedly ground to a halt due to payment disputes.
The scheduled completion date before the latest breakdown was the end of September.
The mayor said urgent finalisation of the project was vital.
“Our dams are today at a combined level of 12.12% and we desperately need to buy time to take pressure off them and prevent them running dry.
“The extra volume we can get from Nooitgedacht will allow us to achieve this goal because it gives us an extra 40ML of water a day, raising our extraction from that source to 210ML per day.
“Surely nothing can be more pressing?
“Yet despite my appeals to the minister of water and sanitation [Senzo Mchunu] and his department and to President Cyril Ramaphosa we have received no positive response,” Bhanga said.
“We will run out of water if we do not manage to get back on track with Nooitgedacht as soon as possible.
“The Amatola Water Board has proved incapable and we have a responsibility to our residents and to make other spheres of government aware of negligence.
“I will fight tooth and nail to prevent our taps running dry.
“If they give us this project, we will manage and complete it efficiently the way we did with phases one and two in 2016/2017.”
Amatola Water spokesperson Nosisa Sogayise said last week the agency had paid over R13.2m on October 8 to Stefanutti Stocks.
This sum includes R1.9m which the contractor had pinpointed as being outstanding.
She said underlying contractual issues were to blame for the continued delay.
Stefanutti Stocks Coastal contracts director John Woodburn confirmed on Sunday that the outstanding money had been paid over but, because termination had already happened due to nonpayment, a new agreement now had to be reached.
The hope was this agreement would still be finalised but feedback was awaited from Amatola Water.